
We commenced work on this site at the end of February 2003 and has now (April 2004) been completed - scroll down to see the running story from start to finish.




New Radius Brick Wall.
Nearing completion.
The biggest shower head in the world! The last time I saw one of these it was on a watering can!
Oak Stairs - all the way from Bradford! What a fantastic job!
Decoration of the top two floors complete.
The decorators are on the ground floor.
The kitchen has arrived!
Mick the sparky! We just don't know where all these wires go, but luckily he does, thank goodness!
Jim is a valuable member of our team!
This is how they used to make Cornice work in the olden days.... Jim can still do it!
Breakfast Room.
Stairs going in.
Stairs going in.
Cement for floor being delivered.
Scaffold down - ready for Stone Porch.
Scaffold down - garage complete.
Roof complete - windows in.
Turret looking good!
Some of the boys who made it possible!
Des - Chief cook and bottle washer!
Topping Out Party! Thanks to Nina and Des for a nice afternoon!
Roof and garage tiled and in the dry!
Chimney being built!
Roof Tiling and Chmineys being built!
Roof Tiling.
Dormers.
Turret progressing.
Roof on - dormers constructed.
What a lot of timber!!
Trusses going on.
Trusses being delivered.
Block and beam floor, finished
Sun coming throught the turret at 8am!
View from hallway to kitchen
Garage roof finished and water-tight
Internal walls at first floor - ready for roof
Close-up of turret, brickwork still to be finished
End of house with turret
Scaffold up, ready for roof
Roof on garage
Safety bags, while concrete floor being erected
First floor - concrete beams
Fireplace
Lounge
View from Hall to Kitchen
Scaffold Up
Scaffold Up
Blockwork up to roof height.
Garage brickwork - ready for scaffold.
Cavity Insulation installed - brickwork growing.
Brickwork being laid to back-up blockwork.
Quality Control found dodgy drainage fitting - must be rejected!
Internal walls started.
Master Blockworker - starting on blockwork.
Brickwork upto DPC.
Loaded out, ready for laying blocks.
Blocks delivered - brickwork started
Drainage installed - septic tank being installed next week
Garage prior to concreting
Installation of Beam and Block Floor
AS IT STANDS AT THE MOMENT (18th March 2003) WATCH THIS SPACE FOR NEXT DEVELOPMENT
GARAGE FOUNDATIONS, READY FOR BLOCKWORK
COMMENCING THE BLOCKWORK
SECOND WEEK - CONCRETE FOUNDATIONS
DIGGING OUT THE FOOTINGS
FIRST DAY AT 'FOXWOOD'

|